Site icon Councillor Stephanos Ioannou

MEQ- Carriageway Improvement works – Willow Walk, N21 [SEC=OFFICIAL]

Dear Councillors,

CARRIAGEWAY IMPROVEMENT SCHEME: WILLOW WALK, N21

As part of Enfield’s investment for 2022/2023 in the Borough’s highway infrastructure, the above road has been identified as requiring reconstructing.

The work is scheduled for : PHASE 1 (GPR SURVEY) – WEDNESDAY 19TH OCTOBER – FRIDAY 21ST OCTOBER 2022 & PHASE 2 (PREP WORKS & CARRIAGEWAY RECONSTRUCTION) – THURSDAY 27th OCTOBER TO FRIDAY 4TH NOVEMBER 2022 (EXCLUDING WEEKENDS) 

The scheduled dates could be subject to change due to any unforeseen circumstances.

Please find attached a copy of the letters explaining the works in full detail which will be delivered to residents.  

Exit mobile version